In short
- A 1.7 tonne mini digger moves about 15 to 30 m³ in a day. A 13 tonne machine moves 200 to 350.
- Trucks, not the digger, usually limit how fast soil leaves a site.
- Rock, wet clay, tight access and working around services can halve the output.
- Dug soil swells 20 to 40 percent, so count truckloads on the loose volume.
In average soil with reasonable access, a 1.7 tonne mini excavator digs about 15 to 30 cubic metres in a day, a 5 tonne machine 50 to 100, a 13 tonne machine 200 to 350, and a 20 tonne machine 400 to 600. Those are volumes measured in the ground for bulk digging. Trenching, trimming and working around obstacles are slower.
Daily output by machine size
| Excavator | Bucket size | Bulk digging per day | Trench per day (600 mm deep) |
|---|---|---|---|
| 1.7 tonne | 0.04 m³ | 15 to 30 m³ | 30 to 60 m |
| 3 to 5 tonne | 0.1 to 0.15 m³ | 50 to 100 m³ | 60 to 120 m |
| 8 tonne | 0.25 to 0.3 m³ | 100 to 180 m³ | 80 to 150 m |
| 13 to 14 tonne | 0.5 to 0.6 m³ | 200 to 350 m³ | 100 to 200 m |
| 20 tonne | 0.9 to 1.0 m³ | 400 to 600 m³ | Mainly bulk work |
Indicative figures for an eight-hour day in firm clay or soil with a competent operator. Real sites vary widely.
Where the numbers come from
Output is bucket size multiplied by the number of cycles. A cycle is dig, swing, dump and return, and a good operator loading a truck completes one every 20 to 30 seconds. A 13 tonne excavator with a half cubic metre bucket could, in theory, move 60 cubic metres an hour. Nobody achieves that across a day. Buckets are not always full, the machine repositions, trucks come and go, levels are checked and people stop for breaks. Working at 50 to 60 percent of the theoretical rate is normal, and that is what the table shows.
What slows an excavator down
- Waiting for trucks. The commonest limit. If the tip is 40 minutes away and there are two trucks, the digger spends most of the day idle. Matching truck numbers to the haul is the main planning job on a digout.
- Ground. Sand and loam fill a bucket easily. Stiff summer clay takes more effort. Wet clay sticks in the bucket. Basalt stops digging altogether until it is broken, and rock breaking yields only a few cubic metres an hour.
- Access and swing room. A machine that can only dump behind itself, or that has to track 30 metres to a stockpile, loses half its cycles.
- Depth and reach. Deep excavations need benching, and digging at full reach is slow.
- Services and structures. Digging beside pipes, cables, footings and trees is done at a crawl, often with someone spotting.
- Precision. Trimming a platform to within 20 mm or a trench to an even fall takes many light passes.
- Weather. Rain stops clay earthworks, and the site may need a day or two to dry.
Bank, loose and compacted volume
Soil has three volumes, and mixing them up is the usual cause of wrong truck counts.
- Bank volume is the soil in the ground. Drawings and quotes use it.
- Loose volume is the soil after digging. Clay swells 20 to 40 percent, rock more.
- Compacted volume is the soil after it is placed and rolled as fill. Clay ends up at about 85 to 95 percent of its bank volume.
So a 100 cubic metre hole produces 120 to 140 loose cubic metres. At 6 to 8 loose cubic metres per 6-wheel truck, that is 17 to 23 loads.
Worked example: a house-site digout
Say a garage and slab cut-down needs 150 cubic metres taken out and removed, on a site where trucks can pull up beside the digger. An 8 tonne excavator can dig that in about a day and a half. The loose volume is around 195 cubic metres, or about 28 truckloads. With a 50-minute round trip to the tip, one truck manages eight or nine loads a day, so three trucks are needed to keep the digger working. Priced by volume, digging at $25 to $60 is $3,750 to $9,000 and cartage at $45 to $110 is $6,750 to $16,500.
Put the same 150 cubic metres behind a villa with a one metre side path and the picture changes. A 1.7 tonne machine and tracked barrows might move 15 cubic metres a day, so the dig takes two weeks, and the rate becomes $120 to $300 per cubic metre.
Choosing the machine
The largest excavator that can comfortably reach and work the site is almost always the cheapest way to move soil. A machine twice the weight costs perhaps 30 percent more per hour and moves three times as much. The exceptions are small volumes, where transport cost dominates, and jobs that are mostly fine trimming or trenching, where a small machine with a skilled operator is ideal. Hourly rates for each size are in the pricing guide, and machine choices are on the digger hire page.
Planning with these numbers
- Work out the bank volume: length by width by average depth.
- Multiply by 1.3 for the loose volume and divide by 7 for truckloads.
- Pick the machine by access, then read the daily output from the table.
- Halve the output if the site is tight, rocky, wet or full of services.
- Check how many trucks are needed to keep up with the digger.
That gives a fair first estimate of days on site. The contractor's site visit turns it into a price.
Common questions
How many cubic metres can a mini digger dig in a day?
A 1.7 tonne mini digger moves about 15 to 30 cubic metres in a day of bulk digging in firm soil. In tight spaces, or when spoil has to be barrowed away, expect the lower end or less.
How long does it take to dig a pool?
An 8 tonne excavator with truck access digs a typical 60 to 80 cubic metre pool in one to two days. With only a mini digger and barrows, allow three to five days.
How many truckloads is 100 cubic metres of soil?
About 17 to 23 loads in a 6-wheel tip truck, because the soil swells to 120 to 140 loose cubic metres and each truck carries 6 to 8.
Does rain stop excavation?
On clay, yes. Wet clay smears, will not compact and makes a mess of roads. Sandy and volcanic soils can be worked in light rain.