In short
- Cut and fill levels a slope by moving soil from the high side to the low side.
- Reusing soil on site costs $20 to $45 per m³, against far more to cart it away.
- Fill under a building must be placed in thin layers, compacted, tested and certified.
- Cut soil shrinks when compacted, so cut and fill volumes are not one for one.
Cut and fill is the method of making level ground on a slope by cutting soil from the high side and placing it as fill on the low side. Done well, the two volumes balance, nothing is trucked away, and the result is a platform that can carry a house. Done badly, the fill settles for years. The difference is in how the fill is placed and compacted.
How it works
Picture a section that falls two metres from back to front. To build a level platform across the middle, the back metre is cut down and the front metre is built up. The line where cut meets fill runs across the site. Uphill of it the platform sits on natural ground that has never been disturbed. Downhill of it the platform sits on soil that was placed by a machine. Each side ends in a slope, called a batter, or in a retaining wall.
Balancing the volumes
A designer aims for a balance, where the cut provides just enough soil for the fill. Three things complicate it.
- Topsoil does not count. It is stripped first and set aside, because it cannot be used as structural fill.
- Soil shrinks when compacted. A cubic metre of clay cut from the ground swells on the truck, then compacts back to about 85 to 95 percent of its original volume as fill. More cut is needed than the fill volume suggests.
- Not all cut is usable. Wet clay, peat, soil full of roots and any rubbish are unsuitable and have to go.
Where the site cannot balance, the surplus is carted away or the shortfall is imported as hardfill. Both cost more than moving soil within the site.
Preparing the ground under fill
Fill is only as good as what it sits on. Vegetation, topsoil and soft material are stripped from the fill area. On a slope, steps called benches are cut into the natural ground so the fill keys in and cannot slide on the old surface. Gullies and wet areas get subsoil drains laid before any fill goes over them, because water trapped under fill softens it from below.
Placing and compacting
- Soil is spread in a layer, typically 150 to 200 mm thick when loose.
- If it is too dry it is dampened, and if too wet it is left to dry or is blended. Clay compacts properly only within a narrow range of moisture.
- The layer is compacted with a sheepsfoot or padfoot roller, or with the tracks of the machine and a plate compactor on small sites.
- The layer is tested.
- The next layer goes on, and the process repeats to the finished level.
Pushing soil over the edge of a slope and tracking across the top is not compaction. End-tipped fill is loose all the way down, and houses built on it crack.
Testing and certification
Structural fill is supervised by a geotechnical engineer. During placement a technician tests each lift, on clay usually with a shear vane and by measuring density and air voids. Scala penetrometer tests are common on the finished surface. At the end the engineer issues a statement or completion report certifying that the fill was built to the specification and stating what bearing capacity foundations can assume. The council asks for it with the building consent. Testing costs $400 to $1,200 a visit, and several visits are normal.
Batters and walls
The edges of the platform have to be held. A cut batter in firm Auckland clay is commonly formed no steeper than about one vertical to two horizontal unless an engineer says otherwise, and fill batters are flatter still. Batters use up land: a two metre high batter at that slope takes four metres of section. Where space is short, a retaining wall replaces the batter. Walls over 1.5 metres, or carrying load, need an engineer and a building consent. Finished batters are topsoiled and grassed or mulched quickly, because bare slopes erode.
Water
A platform changes where water goes. The cut face intercepts groundwater, so a drain at its toe is standard. The platform itself is shaped to shed water away from the building. Runoff from above is turned aside by a cut-off drain so it does not pour over the cut. During construction, sediment controls sit on the low side of the fill, which is where the silt will go.
Why foundations care about the cut-fill line
A house that straddles the line has part of its foundation on natural ground and part on fill. Even well-compacted fill behaves a little differently from natural ground, so engineers design for it: deeper footings on the fill side, a stiffened raft slab, or piles taken through the fill. It is one reason the foundation design waits for the geotechnical completion report.
What cut and fill costs
| Item | Guide price |
|---|---|
| Cut, move and compact as fill on site | $20 to $45 per m³ |
| Dig and load surplus | $25 to $60 per m³ |
| Cart away and tip surplus | $45 to $110 per m³ |
| Imported hardfill, placed and compacted | $90 to $160 per m³ |
| Strip and stockpile topsoil | $6 to $15 per m² |
| Cut-and-fill platform, sloping section | $25,000 to $80,000 |
Guide prices for Auckland before GST, on a site with reasonable access. Only the written quote that follows a site visit is a firm figure.
For 200 cubic metres balanced on site, the earthmoving is $4,000 to $9,000. If the same 200 cubic metres had to be dug and carted away, it would be $14,000 to $34,000.
Consent
Cut and fill is earthworks under the Auckland Unitary Plan, and both the cut and the fill count toward the volume. Larger platforms, steep sites and sites with overlays need a resource consent. See earthworks consent in Auckland. The next step after the platform is covered in the building platform guide, and the service itself is on the residential earthworks page.
Common questions
What does cut and fill mean?
Cutting soil from the high part of a site and placing it on the low part to make level ground. The aim is to balance the two so little or no soil is trucked away.
Can you build a house on fill?
Yes, if it is engineered fill: suitable soil placed in thin layers, compacted, tested and certified by a geotechnical engineer. Uncontrolled fill cannot carry a house without special foundations.
How thick are the layers of fill?
Typically 150 to 200 mm loose thickness per layer for clay, compacted before the next is placed. The engineer's specification sets the figure for each site.
Is cut and fill cheaper than a retaining wall?
Usually, where there is room for batters. Walls are used when the section is too small or too steep for slopes at a safe angle.