In short
- Poles in the ground are H5 treated. Rails and lagging against soil are H4.
- Rule of thumb: as much pole in the ground as wall above it, more on slopes.
- A drain coil and free-draining backfill behind the wall are not optional.
- Built cost is $350 to $600 per m² up to 1.5 m as a guide.
A timber retaining wall is a row of treated poles or posts concreted into the ground, with horizontal rails fixed behind them to hold the soil. It is the most widely built retaining wall in New Zealand because it is economical, quick, and tolerant of the small ground movements that crack rigid walls. Built with the right treatment, depth and drainage, it lasts 20 to 40 years.
The parts of a timber wall
| Part | Typical material | Job |
|---|---|---|
| Poles or posts | Round poles 150 to 250 mm, or square posts, H5 treated | Cantilever out of the ground to resist the soil |
| Rails or lagging | Half-rounds, 150 x 50 or 200 x 50 boards, H4 treated | Span between poles and hold the soil |
| Footing | Concrete around each pole in a drilled hole | Fixes the pole in the ground |
| Drainage | Drain coil, drainage metal, filter cloth | Removes water from behind the wall |
| Fixings | Hot-dip galvanised, or stainless near the coast | Hold rails to poles |
Timber treatment
Radiata pine has no natural durability in the ground, so retaining wall timber is pressure treated to a hazard class set by NZS 3640.
- H5 for poles and posts, which are set in the ground and are structural.
- H4 for rails, lagging and any timber in contact with the ground.
- H3.2 is for timber above ground and exposed to weather, such as fence palings and capping. It is not suitable for the wall itself.
Cut ends should be sealed with preservative, and ideally the cut end of a pole goes up, not into the ground. Using fence-grade timber in a retaining wall is the commonest reason walls rot off at ground level within ten or fifteen years.
Post depth and spacing
A pole wall works as a cantilever: the embedded length of the pole resists the turning force of the soil pushing on the exposed length. The usual rule of thumb is to have at least as much pole in the ground as wall above it. A 1.2 metre high wall has poles about 2.4 metres long, half in the ground. On a slope that falls away in front of the wall, on soft clay or in fill, the embedment goes deeper. Poles are typically spaced 1.0 to 1.2 metres apart, closer for taller walls or lighter rails. Holes are drilled with an auger, 400 to 600 mm in diameter, and filled with concrete around the pole.
These are rules of thumb for low walls on good ground. For anything over 1.5 metres, carrying extra load, or on a difficult site, an engineer calculates the pole size, depth and spacing.
Lean and layout
Poles are usually set leaning back into the bank slightly, around 1 in 10, so that small movements over time bring the wall toward vertical instead of past it. Rails go on the uphill side of the poles, so the soil presses them against the poles and the fixings only have to hold them in place. Rails are butted on pole centres and staggered between rows.
Drainage: the part that decides how long it lasts
Water is heavy, and saturated clay is far heavier and weaker than dry clay. A wall with no drainage has to hold back the soil and the water in it. Every timber wall should have:
- A perforated drain coil along the base behind the wall, laid to fall.
- Free-draining aggregate, such as scoria or drainage metal, at least 300 mm wide up the back of the wall.
- Filter cloth between the aggregate and the soil, so fines do not clog it.
- An outlet to an approved discharge point, not onto the neighbour's land.
The gaps between rails let some water through, but they are not a drainage system. The detail is covered in the subsoil drainage guide.
How a timber wall is built
- Set out the wall line and check boundaries and underground services.
- Cut the bank back far enough to work and to fit the drainage. Spoil is stockpiled for backfill or carted away.
- Drill the holes to depth.
- Stand and concrete the poles, braced to line and lean, and leave the concrete to cure.
- Fix the rails from the bottom up.
- Install drainage: coil, cloth and aggregate, rising with the backfill.
- Backfill in layers. Heavy compaction right behind a new wall is avoided.
- Finish: capping, topsoil, and a fence or barrier if needed.
A straightforward 15 to 20 metre wall takes about a week on site.
Consent rules
Under Schedule 1 of the Building Act, a retaining wall needs no building consent if it retains no more than 1.5 metres of ground and does not support any surcharge or load other than that ground. Surcharge includes a driveway, parking, a building, a pool, another wall above, or ground that slopes up steeply behind. Walls outside the exemption need a consent and an engineer's design. Being exempt from consent does not exempt a wall from the Building Code. Where a person could fall a metre or more from the top, a barrier is required. Planning rules on height near boundaries and on earthworks are separate, and vary by council. In Auckland, confirm with Auckland Council.
Lifespan and maintenance
Expect 20 to 40 years from a well-built wall. The lower figure applies to wet sites and poor drainage, the higher to dry, well-drained ones. Each year, check that the drain outlet is running after rain, that soil has not built up above the top of the wall, that no new load has been added behind it, and that the lean has not changed. Staining or oiling improves the look but does little for the timber below ground, which is where decay happens.
Cost
| Item | Guide price |
|---|---|
| Timber wall up to 1.5 m | $350 to $600 per m² |
| Engineered timber wall over 1.5 m | $600 to $950 per m² |
| Engineer's design | $1,500 to $4,000 |
| Building consent fees | $2,500 to $6,000 |
Guide prices per square metre of wall face, built and drained, before GST, on a site with reasonable access.
A wall 18 metres long and 1.2 metres high is 21.6 square metres, or $7,560 to $12,960 at $350 to $600 per square metre. Full pricing is in the retaining wall cost guide, and Auckland walls are on the retaining walls page.
Common questions
What timber treatment is needed for a retaining wall in NZ?
H5 for poles and posts set in the ground, and H4 for rails and other timber in contact with soil. H3.2 fence timber is not suitable.
How far into the ground do timber wall posts go?
As a rule of thumb, at least as deep in the ground as the wall is high above it, and deeper on slopes, soft ground or fill. Engineered walls follow the engineer's design.
How long does a timber retaining wall last?
About 20 to 40 years with correct treatment and good drainage. Poor drainage and under-treated timber can halve that.
How high can a timber retaining wall be without consent?
It can retain up to 1.5 metres of ground without a building consent, provided it carries no extra load such as a driveway or building. Check local planning rules as well.